MS Project 2016. Getting Started презентация

Содержание

Слайд 2

Start a new project

There are a lot of different templates and themes like

Software development plan and Agile project management.

Start a new project There are a lot of different templates and themes

Слайд 3

The MS Project interface

Toolbar
Ribbon

Main Screen components

The MS Project interface Toolbar Ribbon Main Screen components

Слайд 4

Schedule a Project from a Start or Finish Dates

Schedule a Project from a Start or Finish Dates

Слайд 5

Setting working Days

Setting working Days

Слайд 6

Gantt Chart

Gantt Diagram

Task

Gantt Chart Gantt Diagram Task

Слайд 7

Working with Tasks List

Adding the essential data of tasks :
Task name
Duration (D, W,

H, M, Mo)
Start date
End date
% Complete

Working with Tasks List Adding the essential data of tasks : Task name

Слайд 8

Task Information

Editing task. Adding resource. Changing dates

Task Information Editing task. Adding resource. Changing dates

Слайд 9

Creating Tasks Relationships

MS project will calculate dates based on the durations of the

tasks, their relationships and the start date set for the project, however it is possible to change the starting date of a task (if necessary) By double clicking on a Task or milestone, and using the fields related to the dates (Start or Finish).

Creating Tasks Relationships MS project will calculate dates based on the durations of

Слайд 10

FS Finish-to-Start Relationship

Task/Resources

Successors

Duration

Predecessors

FS

FS Finish-to-Start Relationship Task/Resources Successors Duration Predecessors FS

Слайд 11

SS Start-to-Start Relationship

Task/Resources
Successors

Predecessors

SS

SS Start-to-Start Relationship Task/Resources Successors Predecessors SS

Слайд 12

FF Finish-to-Finish Relationship

Task/Resources
Successors

Predecessors

FF

FF Finish-to-Finish Relationship Task/Resources Successors Predecessors FF

Слайд 13

Lag

Task/Resources

Successors

Predecessors

Lag

Lag Task/Resources Successors Predecessors Lag

Слайд 14

SF Start-to-Finish Relationship

Task/Resources

Successors

Predecessors

SF

SF Start-to-Finish Relationship Task/Resources Successors Predecessors SF

Слайд 15

Overlap

Task/Resources

Successors

Predecessors

Overlap

Overlap Task/Resources Successors Predecessors Overlap

Слайд 16

The Critical Path

CP is the flow of tasks, of which, a delay in

any one of
these tasks will cause a delay to the project.
It is the longest path through the project network diagram and the shortest possible time to complete the project.

The Critical Path CP is the flow of tasks, of which, a delay

Слайд 17

Showing Critical Path

Showing Critical Path

Слайд 18

Project Statistics

Go to File -> Info -> Project Information

Project Statistics Go to File -> Info -> Project Information

Слайд 19

Working with Resources List

You can use the Resource Sheet to create a list

of the people, equipment, and material resources.

Working with Resources List You can use the Resource Sheet to create a

Слайд 20

Assigning Resources to Tasks

Assign Resources Using Task List Resources Name Column

Assigning Resources to Tasks Assign Resources Using Task List Resources Name Column

Слайд 21

Assigning Resources to Tasks

Assign Resources Using Task Information, Resources Tab

Assigning Resources to Tasks Assign Resources Using Task Information, Resources Tab

Слайд 22

Assigning Resources to Tasks

Assign Resources Using Resource Tab

Assigning Resources to Tasks Assign Resources Using Resource Tab

Слайд 23

Over allocated Task Resource

MS Project helps you by giving some “Red man” icons

and yellow exclamation mark when your resource is owerlocated or you have some problems with amounts of money

Over allocated Task Resource MS Project helps you by giving some “Red man”

Слайд 24

Calculate project

Calculate project

Слайд 25

Project Statistics – Cost Updated

Project Statistics – Cost Updated

Слайд 26

Task Usage View

Task Usage View

Слайд 27

Task Form

Task Form

Слайд 28

Resources Form

Resources Form

Слайд 29

Resources Using View

Resources Using View

Слайд 30

Team Planner View

Team Planner View

Слайд 31

Calendar View

Calendar View

Слайд 32

Resource Overview Report

Resource Overview Report

Слайд 33

Cost Overruns Report

Cost Overruns Report

Слайд 34

Printing the Project Map

Printing the Project Map